1) CITY OF FORT WORTH HMAC 2016-4(Jan - June 2017)
Amount: $1,104,778
16,375 lf Curb & Gutter, 26,936 sf Driveway
43,045 sf Sidewalk, 62 Ramps
2)CITY OF LANCASTER, DALLAS COUNTY CDBG STREET IMPROVEMENT (July - Sep 2017)
Amount: $216,478
17,151 lf Curb & Gutter, 2007 sf Sidewalk
4 Ramps
3)CITY OF FORT WORTH HMAC 2017-6 (July - Oct 2017)
Amount: $325,830
5585 lf Curb & Gutter, 11,075 sf Driveway
15,818 sf Sidewalk, 12 Ramps
4) CITY OF CLEBURNE, TX Dot Project (Nov - Dec 2017)
Amount: $60,000
1000 sq yd Sidewalk, 10 Ramps
5) CITY OF FORT WORTH HMAC 2017-10 (Nov 2017 - Ongoing)
Amount: $225,120
5010 lf Curb & Gutter, 8186 sf Driveway
6019 sf Sidewalk, 4 Ramps
6) FORT WORTH TRANSPORTATION AUTHORITY, PHASE V (Dec 2017 - Ongoing)
Amount: $583,944
Bus Pads, Sidewalks, Ramps